CIM ASTM Level 1 Certification Practice Test 2025 – Complete Exam Prep

Question: 1 / 400

Before weighing the measure and sample, what must be done after completing the strike off procedure?

Remove the measure from the scales

Clean all excess concrete from the exterior of the measure

Cleaning all excess concrete from the exterior of the measure is essential before weighing. This practice ensures that only the concrete within the measure is accounted for in the weight measurement. Any excess material adhering to the outside could add unintended weight, leading to inaccuracies in the total measurement. Accurate weighing is critical for achieving precise mixing ratios and for the overall integrity of any concrete testing or mixing process.

Proper preparation of the measuring device enhances the reliability of the results, ensuring that the final concrete mix will meet specified standards and performance expectations. Removing excess concrete also helps maintain the cleanliness and longevity of the measuring equipment, contributing to better maintenance practices. Overall, this step is crucial for producing valid and repeatable test results in accordance with ASTM standards.

Get further explanation with Examzify DeepDiveBeta

Soak the measure in water

Dry the measure thoroughly

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy